Base Coat Construction:
Base Coat Construction: Before applying the base coat, stir thoroughly. Spray, brush, and roll application methods can be used. During base coat application, ensure no sagging or missed areas. Corners should be brushed with a brush. Base coat usage is approximately 0.1–0.12 kg/m².
Base Coat Construction Conditions are the same as ordinary latex paint:
(1) Wall moisture content must be less than 10%. High moisture content will affect the adhesion of the coating film, causing blistering and mottling.
(2) Wall surface pH value must be less than 10. Otherwise, alkaline substances or salt leaching out will cause coating blistering and mottling.
(3) Construction and maintenance conditions: temperature ≥5℃, relative humidity ≤85%.
Primer must be completely dry before proceeding to the next process.