Item No.Construction ContentConstruction Instructions
1.Substrate Preparationa. Ensure the wall has sufficient curing time (more than 28 days) and is fully dry. b. The wall must be stable, flat, dry, clean, and free of floating dust, oil stains. c. Wall humidity must be less than 10%. Wall pH value must be less than 10. d. Walls with old coatings must be tested to confirm good adhesion; otherwise, they must be removed.
N. 2.Putty application (2 coats)The putty troweling must be flat, even, smooth, and dense. Each coat must be sanded flat. Start the next process after 7 days. Theoretical usage: 1-2 kg/m² per coat.
N. 3.Primer application (1-2 coats)Spray the primer to prevent alkaline seepage and contamination of the textured paint. Theoretical usage: 0.12-0.14 kg/m² per coat.